Skip to main content

Cornell University

Cornell University Library Space Projects

Building the Library of the Future

Uris Library and McGraw Tower Envelope Renewal

Aerial view of Uris Library
Aerial view of Uris Library

Project Scope

This project will provide strategic renewal of the Uris Library and McGraw Tower exterior building envelope. This maintenance work is required to prevent deterioration of the Uris Library and McGraw Tower exterior masonry and roofing elements. Work is being performed in a single construction project to maximize efficiency, and access to the building will be maintained throughout the project.

The following high priority envelope renewal items were identified by Mesick Cohen Wilson Baker Architects in the January 2020 Preliminary Building Envelope Condition Assessment:

  1. McGraw Tower: Work includes masonry stabilization and repair, mortar repointing, replacing three different roof systems including the main pyramidal roof, repairing and replacing steel framing and anchors on the pyramidal roof, painting decorative metal grilles, and repair and painting elements of the clock faces.
  2. Uris Library West Wing Bay Roof: Replacement of the original roof system.
  3. Uris Library Main Entrance Porch Roof: Replacement of the current roof system.
  4. Uris Library West and South Wing Gable End Parapets: Repair and replacement of masonry, mortar, copings, and flashings at the parapets.
  5. Uris Library Main East Entrance Steps and North Wall Foundation of Main Reading Room: Reconstruction of the main entrance steps with proper pitch for drainage and repair the north foundation wall with proper water barriers.

Project Schedule

Welliver, General Contractor for the project, mobilized at the base of McGraw Tower and around Uris Library on Friday, July 14, 2023. This work included securing the project site around the tower and staging areas near the library with construction fencing. Installation of scaffolding surrounding the tower began the week of July 31, 2023, and should be complete by the end of September.

McGraw Tower Scaffolding Installation
McGraw Tower Scaffolding Installation

The overall construction schedule runs from mid-July 2023 through the onset of winter weather, pauses until the Spring 2024 construction season begins, and then continues through expected completion by November 2024. General working hours are Monday-Friday, 7:00am-3:30pm.

The pedestrian walkway from Ho Plaza northward to Uris Library, Olin Library, and the Arts Quad have been reopened for the winter. Access to Uris Library via the Tower Entrance will be maintained throughout the duration of the project, with very limited exceptions. Please look for wayfinding and informational signage along the construction fence.

Cornell Chimes activity is limited during construction. Please visit the Cornell Chimes website for more information and an updated concert schedule.

If you have questions, please contact Jon Ladley, Director of Facilities Planning, Cornell University Library

jfl65@cornell.edu

607-255-3569