April 21, 2023

Project team members from Watts Architects & Engineers will be on site beginning at 10:00am on Monday, 4/24 to perform a site survey of the Olin Library exterior The areas to...

April 5, 2023

Project team members from Goody Clancy will be on site beginning at 8:15am on Thursday, 4/6 to scan Olin Library spaces for 3D imaging This work will continue throughout the day,...

March 27, 2023

Project team members from CUL and Code Red Consultants will conduct a walkthrough of Olin 1, B, and 2B to do a building code analysis for the upcoming project beginning at 8:30am...