Project team members from RFS Engineering will be on site beginning at 8:30am on Thursday, 6/22 to continue detailed field work for the Olin mechanical upgrades The work will...

June 5, 2023

Project team members from RFS Engineering will be on site beginning at 8:30am on Tuesday, 6/6 to complete detailed field work for the Olin mechanical upgrades The work will...

May 12, 2023

May 12, 2023

May 12, 2023

May 12, 2023

April 25, 2023

What does the Olin basement and first floor renewal mean specifically for the basement collections  • Due to its weight, the map collection will stay in the basement We will...

April 21, 2023

Project team members from Watts Architects & Engineers will be on site beginning at 10:00am on Monday, 4/24 to perform a site survey of the Olin Library exterior The areas to...

April 5, 2023

Project team members from Goody Clancy will be on site beginning at 8:15am on Thursday, 4/6 to scan Olin Library spaces for 3D imaging This work will continue throughout the day,...

March 27, 2023

Project team members from CUL and Code Red Consultants will conduct a walkthrough of Olin 1, B, and 2B to do a building code analysis for the upcoming project beginning at 8:30am...