1/28/11 Update

The project will soon be entering the last construction phase for the first floor. Phase 9 construction (west end of 110, 111 and 101 offices, Periodical Room) will begin the week of February 7. In preparation, periodicals from the 101 Current Periodical Room were moved to the Willis Room in Uris Library on February 26. […]

1/24/11 Update

The following is planned for the week of January 24: Wednesday, January 26 — Reference Desk across from the public computing area reopens Wednesday, January 26 – Current periodicals will be temporarily relocated to the Willis Room (directional signs will be posted) in preparation for upcoming construction in 101 offices

1/17/11 Update

Highlights for week of January 17: Monday, January 17 — Café opens January 17. Monday, January 17 — 1st floor corridor on the west end (Uris end) to public elevators reopens. Monday, January 17 — Staircase to basement next to Café entrance reopens. Monday, January 17 – Friday, January 21 — An air handler will […]

1/7/11 Update

The following are the highlights of the schedule for January 10 – 15: Monday, January 10 — Reoccupy public computer area across from the Reference Desk. Tuesday, January 11 – Wednesday, January 12 — Close Reference Reading Room on the north side of the first floor. Wednesday, January 12 — Disassemble entrance scaffolding. Wednesday, January […]

Update Categories