12/14-20/10 Update

Schedule for 1st and 5th floor staff, services and operations (see 1st floor phases below)

  • 12/14:  Open 5th floor stacks
  • 12/15:  Olin/Uris Admin and R&LS staff move back to 106
  • 12/16: Café closes at noon
  • 12/16: Staff move back to 501
  • 12/17: Front entrance closes/temporary entrance on north side opens
  • 12/17:  Photographer taking pre-construction photographs of 1st floor public and staff spaces
  • 12/17: Staff temporarily move to 218 and 110 west and 701
  • 12/20: 18 public computers relocated to north side (reference reading room) and public computing area on south side closes
  • 12/20:  Circulation Desk and Offices (115 and 116) close and operations relocate to Uris except for minimal circulation services at Olin Reference Desk and discharging in Olin B42 Collection Maintenance office

1ST FLOOR CONSTRUCTION PHASES*

  • 6A – 106 suite and classroom – Nov. 11 – Dec. 16, 2010
  • 6B – Café – Dec. 17, 2010 – Jan. 14, 2011 (closing Dec. 16 noon and reopening Jan. 17, 2011)
  • 6C – Reading Room North – Jan. 12 – Feb. 4, 2011
  • 7A – Entrance and Front Lobby – Dec. 17, 2010 – Jan. 21, 2011
  • 7B – Circulation Desk Area and Offices (115 + 116) – Dec. 20, 2010 – Jan. 13, 2011
  • 7C – Reference Desk Area (104 and 105) – Jan. 14 – 26, 2011
  • 8A – Information Commons (public computers) Dec. 17, 2010 – Jan. 11, 2011
  • 8B – Southeast (107, 107A-E, east end of 110) Dec. 17, 2010 – Feb. 7, 2011
  • 9    – Southwest (101 offices, Periodical Room 111, 110 west) – Feb. 8 – April 5, 2011

*Note:  Dates represent time allotted for moving as well as actual construction. Schedule is subject to change.