November 21: Plant Science Renovation Update

Project Brief

This gut renovation project will reconfigure floor layouts, restore the exterior building envelope, replace the exterior windows, replace the Mechanical, Electrical, Plumbing & Life Safety systems, and generally modernize the facility to meet the School of Integrative Plant Science’s Instructional and Research needs in the 21st century.

  • The project obtained B&P’s Construction Approval on March 23, 2023.
  • FAHS Construction is the General Contractor.
  • The 30-month Construction period began on July 5, 2023, and is scheduled for substantial completion in January 2026.

Progress Report                                                                                                                         

  • Asbestos abatement has now been completed on the Ground, 1st, 2nd and 3rd floors.
  • Selective demolition has largely been completed on the Ground, 1st, 2nd and 3rd floors.
  • Mass demolition has been completed on the Ground and 1st floors.

Two-week look ahead

  • Installation of temporary power and lights will continue through the next two weeks.
  • Mass demolition is in progress on 2nd floor.
  • Selective demolition on 3rd & 4th floors will continue through the next two weeks.
  • Asbestos abatement on the 4th floor has begun and will be on-going for the next two weeks.
  • Installation of the formwork and rebar for the Mechanical Shaft and the Elevator Pit foundation is in progress.
  • Relocation of the RO/DI system to PSB 403B:
    • Abatement in PSB 403B is has been completed.
    • Coring of the floor drain will be done on Nov 22
    • System relocation is planned for a two-week window after Dec 6. To be coordinated w/SIPS.

Upcoming shut-downs

  • The RODI system will be shut-down for relocation between Dec 6 and 20.
construction pit
Formwork and Rebar for the Mechanical Shaft’s Foundation on Ground Floor.
construction pit
Formwork and Rebar for the Elevator Pit on Ground Floor
concrete floor
Mass demolition on First floor, View of the West corridor
chair in hall
Asbestos abatement completed – Third-floor corridor. View of the EW corridor
columns in construction zone
Ongoing selective Demolition – 4th floor lab