Skip to main content

Discovery that Connects

Science-based innovation for a changing world

November 13: Plant Science Renovation Update

Project Brief

This gut renovation project will reconfigure floor layouts, restore the exterior building envelope, replace the exterior windows, replace the Mechanical, Electrical, Plumbing & Life Safety systems, and generally modernize the facility to meet the School of Integrative Plant Science’s Instructional and Research needs in the 21st century.

  • The project obtained B&P’s Construction Approval on March 23, 2023.
  • FAHS Construction is the General Contractor.
  • The 30-month Construction period began on July 5, 2023, and is scheduled for substantial completion in January 2026.

Progress Report

  • Asbestos abatement has now been completed on the Ground, 1st and 2nd floors.
  • Selective demolition has largely been completed on the Ground and 1st floors.

Look ahead

  • Installation of temporary power and lights will continue through the next two weeks.
  • De-energization of the electrical circuits will continue through the next two weeks.
  • Mass demolition is in progress on the Ground and 1st floors.
  • Selective demolition on 3rd & 4th floors will continue through the next two weeks.
  • Asbestos abatement on the 3rd floor should be completed by Friday, November 17th.
  • Asbestos abatement on the 4th floor is scheduled to begin by Monday, November 20th.
  • Relocation of the RO/DI system to PSB 403B:
    • Abatement in PSB 403B is has been completed.
    • Coring of the floor drain is scheduled to begin on Nov. 22nd.
    • Relocation of the system is planned for a two-week window after Dec. 6th. To be coordinated w/SIPS
  • No utility shutdowns have been scheduled for the next two weeks.
reno photo
Progress – Mass demolition on Ground floor. View from the corridor towards the West Entrance (Academic Surge Buildings side)
reno photo
Progress – Formwork for the Elevator Pit on Ground Floor.
reno photo
Progress – On going mass demolition on First floor, View of the West corridor.
Skip to toolbar