Project Brief
This gut renovation project will reconfigure floor layouts, restore the exterior building envelope, replace the exterior windows, replace the Mechanical, Electrical, Plumbing & Life Safety systems, and generally modernize the facility to meet the School of Integrative Plant Science’s Instructional and Research needs in the 21st century.
- The project obtained B&P’s Construction Approval on March 23, 2023.
- FAHS Construction is the General Contractor.
- The 30-month Construction period began on July 5, 2023, and is scheduled for substantial completion in January 2026.
Progress Report
- Asbestos abatement has now been completed on the Ground, 1st and 2nd floors.
- Selective demolition has largely been completed on the Ground and 1st floors.
Look ahead
- Installation of temporary power and lights will continue through the next two weeks.
- De-energization of the electrical circuits will continue through the next two weeks.
- Mass demolition is in progress on the Ground and 1st floors.
- Selective demolition on 3rd & 4th floors will continue through the next two weeks.
- Asbestos abatement on the 3rd floor should be completed by Friday, November 17th.
- Asbestos abatement on the 4th floor is scheduled to begin by Monday, November 20th.
- Relocation of the RO/DI system to PSB 403B:
- Abatement in PSB 403B is has been completed.
- Coring of the floor drain is scheduled to begin on Nov. 22nd.
- Relocation of the system is planned for a two-week window after Dec. 6th. To be coordinated w/SIPS
- No utility shutdowns have been scheduled for the next two weeks.