Schedule

Olin Fire Safety Improvements Project
– Construction Phases

This schedule reflects the latest plan for the order of the construction phases and the general time of year when the listed area of the library will be under construction.  Even though a phase is listed as “completed,” the possibility of some additional work in that area remains before the project is formally designated as completed.  The schedule will be subject to change throughout the project. See updates for more details throughout construction.

CONSTRUCTION SCHEDULE:

Phase

Description Duration

1

2nd floor temporary surge space, east egress, and corridor ceiling Completed

2A + 3

Basement Completed

2B

Sub-basement Completed

4

Penthouse (locked 8th floor) and 7th floor Completed

5

5th floor  (DLIT suite) 501-504 Olin, and
6th floor
Completed

6A

106 suite & classroom Completed

6B

Café Completed

6C

1st floor Reading Room North (103 Olin) Completed

7A

Entrance and part of front lobby Completed

7B

Circulation desk and offices Completed

7C

Reference Desks, Consulting Room, and Printing Area (rooms 104 + 105) Completed

8A

1st floor – 126 (public computers) Completed

8B

1st floor – Southeast (107, 107A-E, east end of 110) Completed

9

1st floor – Southwest (101 offices, Periodical Room 111, 110 west) Completed

10

4th floor & 3rd floor, including West-end meeting rooms Completed

11

2nd floor North (Rooms 206 & 212 – Staff kitchen & lounge; 213 – Communications; 214 – Facilities; 215 – RAU) Completed

12

2nd floor West Admin offices (Suite 201 & Rooms 234 & 235 – LHR & Accounting) Substantially Complete