Schedule
Olin Fire Safety Improvements Project
– Construction Phases
This schedule reflects the latest plan for the order of the construction phases and the general time of year when the listed area of the library will be under construction. Even though a phase is listed as “completed,” the possibility of some additional work in that area remains before the project is formally designated as completed. The schedule will be subject to change throughout the project. See updates for more details throughout construction.
CONSTRUCTION SCHEDULE:
Phase |
Description | Duration |
1 |
2nd floor temporary surge space, east egress, and corridor ceiling | Completed |
2A + 3 |
Basement | Completed |
2B |
Sub-basement | Completed |
4 |
Penthouse (locked 8th floor) and 7th floor | Completed |
5 |
5th floor (DLIT suite) 501-504 Olin, and 6th floor |
Completed |
6A |
106 suite & classroom | Completed |
6B |
Café | Completed |
6C |
1st floor Reading Room North (103 Olin) | Completed |
7A |
Entrance and part of front lobby | Completed |
7B |
Circulation desk and offices | Completed |
7C |
Reference Desks, Consulting Room, and Printing Area (rooms 104 + 105) | Completed |
8A |
1st floor – 126 (public computers) | Completed |
8B |
1st floor – Southeast (107, 107A-E, east end of 110) | Completed |
9 |
1st floor – Southwest (101 offices, Periodical Room 111, 110 west) | Completed |
10 |
4th floor & 3rd floor, including West-end meeting rooms | Completed |
11 |
2nd floor North (Rooms 206 & 212 – Staff kitchen & lounge; 213 – Communications; 214 – Facilities; 215 – RAU) | Completed |
12 |
2nd floor West Admin offices (Suite 201 & Rooms 234 & 235 – LHR & Accounting) | Substantially Complete |