2/24/11 Update

In preparation for the asbestos abatement that will be part of the upcoming 3rd and 4th floor phase 10 construction, the contractor will be taking air samples on those floors the morning of Thursday, February 24. Sampling on the east end (Stimson side) will last until approximately 11:30 am. The west end (Uris side) sampling should be completed earlier. Phase 10 is scheduled to begin on March 9, when the 4th floor will close. The 3rd floor will close on March 11.