6/23/2011 Update

The project is substantially complete and all floors are open. However, in addition to a number of remaining tasks on the punch list there will continue to be some construction related to project in various parts of the building. Information about that work will be posted once it is available.

6/13/2011 Update

Schedule: •    Construction continues on the last phase of the project, i.e. the west end of the 2nd floor •    Anticipated project completion date – Early July, 2011 Additional Related Construction: •    6th floor façade restoration: LeCesse will replace the limestone panels that were removed as part of the façade investigation for the cancelled Olin […]