5/27/11 Update
Construction continues on the second floor. However, the rest rooms and the staff lounge are now open. Administrative staff are temporarily located on the south side of the floor accessible via the east staircase located just before the entrance to Kroch. The 3rd floor opened on May 6 as planned. All stack floors are open.
5/4/2011 Update
The third floor is now scheduled to open on Friday, May 6.
5/2/2011 Collections Update
The 4th floor is now open and call numbers G-H are freely accessible to the public. The collections from the 4th floor reading rooms will be returned to the basement by the end of the week. The 3rd floor is still closed and call numbers PH-PZ are still being paged by staff. The floor is […]
5/2/2011 Update
The fourth floor opened on Friday, April 29. The third floor is scheduled to open on Tuesday, May 10. The north and west sides of the second floor are currently under construction.