7/19/10 Update
7/19/10 – Work is progressing in rooms B12, B42 and the sub-basement; work should begin in the second floor staff space this week. Please refer to phasing schedule online – https://blogs.cornell.edu/firesafety/schedule/
Olin Library Fire Safety Improvemnts Updates
7/19/10 – Work is progressing in rooms B12, B42 and the sub-basement; work should begin in the second floor staff space this week. Please refer to phasing schedule online – https://blogs.cornell.edu/firesafety/schedule/