10/25/10 Update

The following is an update regarding the 7th, 6th, and 5th floors:

  • The 7th floor is in the final stages of construction. The current plan is to open the floor on Tuesday, November 2, at 8 a.m.
  • The 6th floor remains closed to the public and staff as construction on that floor continues. Pending any unforeseen conditions, the floor is tentatively scheduled to reopen on or about Friday, November 19. The exact date will be confirmed later in November.
  • At this point all 5th floor staff, faculty study, and carrel holders have been relocated and preliminary set up work started in the 501 office suite on the west end of the floor. On Monday, November 1 at 6 a.m. the 5th floor will completely close and construction will begin. The floor is tentatively scheduled to reopen no later than December 17. The exact date will be confirmed later.

Outside the building the week of October 25:

  • Excavation on the west end of the building for a new sprinkler connection.