August 15: Plant Science Renovation Update

Project Brief

This gut renovation project will reconfigure floor layouts, restore the exterior building envelope, replace the exterior windows, replace the Mechanical, Electrical, Plumbing & Life Safety systems, and generally modernize the facility to meet the School of Integrative Plant Science’s Instructional and Research needs in the 21st century.

  • The project obtained B&P’s Construction Approval on March 23, 2023.
  • FAHS Construction is the General Contractor.
  • The 30-month Construction period began on July 5, 2023, and is scheduled for substantial completion in December 2025.

Progress Update

  • The project is still on track for substantial completion in December 2025.
  • Installation of Lab casework is on-going on the Ground, First and Second floors.
  • Installation of the ceiling grid is on-going on the Ground and First and Second floors.
  • The AV Integrator is now on board. Coordination with the electrical and other sub-contractors has begun.
  • The interior Signage package will go to bid within the next two weeks.
4th floor progress
4th floor progress
view of central stair with new window
2nd floor progress
ground floor progress