June 20: Plant Science Renovation Update

Project Brief

This gut renovation project will reconfigure floor layouts, restore the exterior building envelope, replace the exterior windows, replace the Mechanical, Electrical, Plumbing & Life Safety systems, and generally modernize the facility to meet the School of Integrative Plant Science’s Instructional and Research needs in the 21st century.

  • The project obtained B&P’s Construction Approval on March 23, 2023.
  • FAHS Construction is the General Contractor.
  • The 30-month Construction period began on July 5, 2023, and is scheduled for substantial completion in December 2025.

Progress Update

  • The project is still on track for substantial completion in December 2025.
  • Final Punchlist walkthrough for the facade restoration will be performed beginning the week of June 23rd.
  • The new north facing large Palladian window will be installed beginning the week of June 23rd.
  • Lab Casework are scheduled for delivery the week of July 7th.

Upcoming shut-downs

  • A full building power shutdown that was originally scheduled for Fall ’24 has been rescheduled for Mid-July ’25.
4th floor
3rd floor
2nd floor
2nd floor
1st floor
ground floor
ground floor

exterior

 