May 1: Plant Science Renovation Update

Project Brief

This gut renovation project will reconfigure floor layouts, restore the exterior building envelope, replace the exterior windows, replace the Mechanical, Electrical, Plumbing & Life Safety systems, and generally modernize the facility to meet the School of Integrative Plant Science’s Instructional and Research needs in the 21st century.

  • The project obtained B&P’s Construction Approval on March 23, 2023.
  • FAHS Construction is the General Contractor.
  • The 30-month Construction period began on July 5, 2023, and is scheduled for substantial completion in January 2026.

Two-week look ahead

  • Demolition of the old west stair has been completed.
  • Installation of new utility piping in the tunnel will continue through the next three weeks.
  • Installation of Fire Alarm conduit will continue through the next three weeks.
  • Removal of lead paint from the beams and columns will continue through the next two weeks.
  • Masonry cleaning is ongoing along the west elevation of the building.
  • Installation of new partitions has begun on the 1st, 2nd and 3rd floors.
  • Installation of exterior scaffolding (to be used for masonry restoration and exterior window replacement) is expected to continue through the next two weeks.
  • Removal of the existing roof ballast via a vacuum truck (a noisy task) has been re-scheduled for Wednesday and Thursday; May 1 and 2.

Upcoming shut-downs

  • Chilled Water shutdown has been scheduled for Wednesday, May 8.
  • Pre-shutdown coordination meeting for the upcoming domestic water shutdown has been scheduled for Friday, May 3.
open stair
Demolition of the old west stair well.
red columns
Removal of lead paint from the beams and columns. The reddish paint on the left column contains lead. The lead paint has been removed from the dark brown column on the right.
building exterior
Masonry cleaning along the west elevation of the building. Progress from the left to the right
open stair
Demolition of the old west stair well has been completed
construction with columns
Progress – New partition tracks on first floor, EW corridor.
construction
Completed elevator shaft enclosure on the 4th floor.