Project Brief
This gut renovation project will reconfigure floor layouts, restore the exterior building envelope, replace the exterior windows, replace the Mechanical, Electrical, Plumbing & Life Safety systems, and generally modernize the facility to meet the School of Integrative Plant Science’s Instructional and Research needs in the 21st century.
- The project obtained B&P’s Construction Approval on March 23, 2023.
- FAHS Construction is the General Contractor.
- The 30-month Construction period began on July 5, 2023, and is scheduled for substantial completion in January 2026.
Progress Report
- Asbestos abatement has now been completed on the Ground, 1st and 2nd floors.
- Selective demolition has largely been completed on the Ground and 1st, 2nd and 3rd floors.
- Mass demolition has been completed on the Ground, 1st and 2nd floors.
- The footing and foundation of the elevator have been completed.
- Mass demolition has been completed on the Ground, 1st and 2nd floors.
Two-week look ahead
- Installation of temporary power and lights will continue through the next two weeks.
- Mass demolition on the 3rd floor is scheduled to begin on Dec. 11
- Asbestos abatement is on-going on the 4th and is scheduled to be completed by Dec. 6
- Relocation of the RO/DI system to PSB 403B:
- Coring of the floor drain was completed on Nov. 22
- Installation of the piping is in progress.
- System relocation was moved from the original Dec. 6 date to Dec. 18
Upcoming shut-downs
- The RODI system will be shut-down for relocation between Dec. 11 and 18