Skip to main content

Discovery that Connects

Science-based innovation for a changing world

August 29: Plant Science Renovation Update

This gut renovation project will reconfigure floor layouts, restore the exterior building envelope, replace the exterior windows, replace the Mechanical, Electrical, Plumbing & Life Safety systems, and generally modernize the facility to meet the School of Integrative Plant Science’s Instructional and Research needs in the 21st century.

  • The project obtained B&P’s Construction Approval on March 23, 2023.
  • FAHS Construction is the General Contractor.
  • The 30-month Construction period began on July 5, 2023, and is scheduled for substantial completion in December 2025.

Progress Update

  • The project is still on track for substantial completion in December 2025.
  • Lab casework installation is in progress on the Ground, First, Second, and Third floors.
  • Ceiling grid installation is in progress on the Ground, First, Second, and Third floors.
  • Coordination of AV integration with the electrical subcontractor and furniture vendor is ongoing.

Upcoming shut-downs

  • None
roof view
3rd floor
Central stair from 3rd floor
2nd floor
2nd floor
1st floor
Ground floor
Exterior
Skip to toolbar