Project Brief
This gut renovation project will reconfigure floor layouts, restore the exterior building envelope, replace the exterior windows, replace the Mechanical, Electrical, Plumbing & Life Safety systems, and generally modernize the facility to meet the School of Integrative Plant Science’s Instructional and Research needs in the 21st century.
- The project obtained B&P’s Construction Approval on March 23, 2023.
- FAHS Construction is the General Contractor.
- The 30-month Construction period began on July 5, 2023, and is scheduled for substantial completion in December 2025.
Progress Update
- The project is still on track for substantial completion in December 2025.
- Installation of Lab casework is on-going on the Ground, First and Second floors.
- Installation of the ceiling grid is on-going on the Ground and First and Second floors.
- The AV Integrator is now on board. Coordination with the electrical and other sub-contractors has begun.
- The interior Signage package will go to bid within the next two weeks.