Project Brief
This gut renovation project will reconfigure floor layouts, restore the exterior building envelope, replace the exterior windows, replace the Mechanical, Electrical, Plumbing & Life Safety systems, and generally modernize the facility to meet the School of Integrative Plant Science’s Instructional and Research needs in the 21st century.
- The project obtained B&P’s Construction Approval on March 23, 2023.
- FAHS Construction is the General Contractor.
- The 30-month Construction period began on July 5, 2023, and is scheduled for substantial completion in January 2026.
Progress Report
- Asbestos abatement has now been completed on the Ground, 1st, 2nd, 3rd and 4th floors.
- Selective demolition has been completed on the Ground, 1st, 2nd , 3rd and 4th floors.
- Mass demolition has been completed on the Ground, 1st, 2nd , 3rd and 4th floors.
- The footing and foundation of the elevator have been completed.
- The footings and foundation for the Mechanical shafts, the West Stair, and other utilities are in progress.
Two-week look ahead
- Installation of temporary power and lights will continue through the next two weeks.
- Saw cutting and slab removal for various utilities on the Ground floor will run from Jan. 22nd through Jan. 26th. · Demolition of the ceiling at the 1st, 2nd, and 3rd floor lobbies are on-going and should be completed by Jan. 26th.
- The filling of trenches left after the removal of the old partitions and the leveling of the existing floors are in progress and will continue through early February.
Upcoming shut-downs
- The Chilled Water and Glycol should be back on-line by Tuesday, January 23rd.