January 21: Plant Science Renovation Update

Project Brief

This gut renovation project will reconfigure floor layouts, restore the exterior building envelope, replace the exterior windows, replace the Mechanical, Electrical, Plumbing & Life Safety systems, and generally modernize the facility to meet the School of Integrative Plant Science’s Instructional and Research needs in the 21st century.

  • The project obtained B&P’s Construction Approval on March 23, 2023.
  • FAHS Construction is the General Contractor.
  • The 30-month Construction period began on July 5, 2023, and is scheduled for substantial completion in January 2026.

Progress Report

  • Asbestos abatement has now been completed on the Ground, 1st, 2nd, 3rd and 4th floors.
  • Selective demolition has been completed on the Ground, 1st, 2nd , 3rd and 4th floors.
  • Mass demolition has been completed on the Ground, 1st, 2nd , 3rd and 4th floors.
  • The footing and foundation of the elevator have been completed.
  • The footings and foundation for the Mechanical shafts, the West Stair, and other utilities are in progress.

Two-week look ahead

  • Installation of temporary power and lights will continue through the next two weeks.
  • Saw cutting and slab removal for various utilities on the Ground floor will run from Jan. 22nd through Jan. 26th. · Demolition of the ceiling at the 1st, 2nd, and 3rd floor lobbies are on-going and should be completed by Jan. 26th.
  • The filling of trenches left after the removal of the old partitions and the leveling of the existing floors are in progress and will continue through early February.

Upcoming shut-downs

  • The Chilled Water and Glycol should be back on-line by Tuesday, January 23rd.
construction with cement floor
Progress – EW corridor on the 4th floor
construction with plastic barrier
Progress – Ceiling demolition, 3rd floor lobby
columns
Progress – West, NS corridor on the 3rd floor.
columns and floor treatment
Progress – application of vapor barrier on the northside of the EW corridor on 1st floor.
stairwell pit
Progress – Backfilling the fiundation at the new west stair