Construction Updates, Latest

Over the past two weeks, crews completed glass window installation on the west elevation at level three. They also completed sealing Zahner clips and started installing the exterior metal Zahner panels at the south elevation. Work continued on grinding the ground level concrete floor, wall framing on all levels, as well as sheetrock on levels [ Read More ]

As the winter chill held on in Ithaca, it was perhaps comforting news that crews started installing tubing for radiant in floor heat on the ground level and window glass on the south elevation at levels two and three this past week. Work also continued on installing exterior window clips, polishing concrete floors on levels [ Read More ]

Exterior glass installation continued over the past two weeks with crews completing the north elevation first floor and east elevation. They also prepped and poured parts of the ground level slab, poured the west metal pan stairs, completed the temporary roof installation, and installed chilled water valves in the existing manhole. Work also continued on [ Read More ]

Over the past two weeks crews poured the first floor far west deck, the auditorium structural slab and parts of the floor on levels three and four. In addition they started forming the remainders of the first, second and third floor decks and continued grinding work on the level one concrete floor. Crews also continued [ Read More ]

November 4: Crews neared completion of the steel structure with work continuing on derricks 22 and 23 this week. Also completed were the installation of the roof deck and the pouring of the third floor deck. The installation of protective curtain walls also continued as did work on the mechanical rough ins at the basement [ Read More ]

Dinosaur Bar-B-Que – a famous central New York delicacy – and cake greeted construction staff as they gathered today to celebrate the “topping off” of Bill & Melinda Gates Hall. Computing and Information Science Dean Dan Huttenlocher thanked members of Iron Workers Local #60 after they hoisted and riveted into place the final structural steel [ Read More ]

October 21: This week crews began the construction of the truss that will form the iconic west end front overhang of Gates Hall by installing the shoring towers and completing the erection of steel through derrick 21. The first floor deck was also poured this week and the electrical equipment was set in the switch [ Read More ]

Crews spent a long Saturday on October 10 completing the truss structure for the signature overhang that will cover the Gates Hall entry plaza along Hoy Road. The structure will offer multiple views of the unique entry plaza which was designed with a nod to the rugged landscape surrounding the Ithaca campus which features stunning [ Read More ]

October 7: This week crews completed pouring foundation walls at the west end of the ground level and the basement slab on grade. In addition, they continued the erection of structural steel — completing work for derricks 10 – 13 — and continued waterproofing basement and ground level walls.             [ Read More ]

September 23: Crews this week completed slab on grade prep in the basement. Work on excavating and pouring grade beams at the site’s west end continued, as did the forming and pouring of the remaining foundation walls. Finally crews continued erecting structural steel on derricks five through seven. September 30: This week crews completed the [ Read More ]