Bill and Melinda Gates Hall powered up this week as crews energized the main power to the building. On the outside of the building crews also started installing storm and sewer lines on the south side of the site and forming and pouring the east site stairs. They also continued installing finished roofing and Zahner panels on the west and north sides of the building. On the inside, from the top down, crews continued taping and spackle on the fourth floor, sheetrock and floor polishing on levels three and four, wall framing on level one, and mechanical rough ins and insulation on all floors. Finally, crews started installing the large and small skylights.