Construction Updates, Latest

Over the past two weeks, crews completed work on Hoy Road to bring all utilities to the site. They also finished the installation of glass on the north elevation at levels two and three and acoustical ceiling insulation on level three, completed soffitt work on the first level’s south side, and formed and poured the remainder of the concrete walls at the south areaway. From the bottom up, crews also continued polishing the ground level concrete floor, installing sheetrock on levels two, three and four; taping and spackling on level four; installing Zahner panels on the north elevation; and creating mechanical and electrical rough in throughout. Finally, underground utility work was started on the west side of the site and glass installation was begun on level four of the north elevation.